Dear Christ Church Family,
We wanted to update you on how the Youth Building construction is coming along.
The Contractor is moving at the scheduled pace that he anticipated.
The footings, foundations, underground utilities and concrete slab are scheduled to be complete mid-August.
The Metal Building is scheduled to arrive by the end of August
The Metal Building will be erected by September 20th.
Interior finishing and offices will be done during October and November
Finish out of the building and Occupancy by Christmas.
So by Christmas of this year we will have completed the building process that we have been in for these past couple of years.
Please give thanks to God for the commitment that each member of CCE has had to this building program.
May we use it to further the Kingdom.